230 Volt AC Power Sequencer
370-1027 |
370-1155 |
Pulizzi Engineering PC874 |
Pulizzi Engineering PC874 |
Outlet Side

Control Side

Notes
- Requires AC outlet NEMA L6-30R, 30A, 250V.
- Any conversion to the Data Center Cabinet, including replacement of the AC
Power Plug or AC Power Sequencer, voids all safety agency approvals.
- The Switched 2 output of 370-1127 comes on after a 5-second delay.
- The Switched 2 output of 370-1155 comes on after a 20 sec delay.
References
- Sun Full-Height Rack System Installation Manual, 800-1677.
- Sun Rackmountable Fileservers Installation Manual, 800-1676.
- Sun 900 Mbyte Disk Drive Installation Manual, 800-1036.
- Sun 56-inch Data Center Cabinet and Data Center Expansion Cabinet
Installation Manual, 800-3242.
- Sun 56-inch Expansion Cabinet Installation Manual, 800-5936-18.
- Sun 56-inch Cabinet Service Manual, 800-6371-17.
Last updated: December 2, 1996
|